Pick the work, enter its wet volume, and get the sand needed. For plaster, multiply the area by the thickness to get the volume first, or use the plaster calculator.
1 m³ = 35.3 cu ft
Sand needed: –
How it is calculated
Dry volume = wet volume × 1.54 for concrete or × 1.33 for mortar and plaster, to allow for voids and bulking. Sand = dry volume × sand parts ÷ total parts, plus wastage. 1 brass = 100 cu ft.
Worked example
1 m³ of M20 concrete: dry volume 1.54 m³; sand is 1.5 of 5.5 parts, so 0.42 m³, about 14.8 cu ft, or 0.15 brass before wastage.
Related: Concrete calculator · Cement quantity calculator · M-sand · Brass (unit)