Enter a dry-mix volume and the mix ratio to get the cement bags needed. For wet concrete use the concrete calculator.
1:4 mortar is 5 parts; 1:6 is 7 parts; 1:1:2 concrete is 4 parts
–
How it is calculated
Cement volume = dry volume × (cement parts ÷ total parts). Cement bags = cement volume ÷ 0.0347 m³ per 50 kg bag. Wastage is added and the result is rounded up.
Worked example
1 m³ of dry 1:4 mortar has 5 total parts and 1 cement part. Cement volume = 1 × 1 ÷ 5 = 0.2 m³, which is 5.8 bags, so 6 bags with wastage.
FAQs
Where do I get the dry volume? For plaster, use the plaster calculator. For concrete, use the concrete calculator, which applies the 1.54 factor for you.
Are bags always 50 kg? Most are. Check the bag weight before ordering.