Enter the plinth area of one floor and the number of floors. You get a rough bill of materials for the whole house. Add your dealer’s rates to see the material cost.
Add your dealer’s rates (optional)
Current indicative rates: cement in Hubballi-Dharwad · TMT steel in Hubballi-Dharwad. Always confirm with your dealer.
| Material | Quantity | Cost |
|---|
Total built-up area: – · Material cost: –
Rough thumb-rule estimate for budgeting and checking contractor orders. Your structural engineer’s drawings decide the real quantities.How it is calculated
Total built-up area = area per floor × floors. Then we apply common Indian thumb rules per sq ft of built-up area, explained in our guide to material quantity per 1,000 sq ft:
- Cement: about 0.4 bags per sq ft.
- Steel: about 3.5 kg per sq ft for a ground-floor house, rising to about 4 kg for G+1 and 4.5 kg for G+2 or more, because lower columns and footings carry more load.
- Sand: about 1.8 cu ft per sq ft (shown in brass; 1 brass = 100 cu ft).
- Aggregate (jelly): about 1.35 cu ft per sq ft.
- Bricks: about 8 per sq ft. AAC blocks (600 × 200 × 200 mm) replace roughly 9 bricks each, so we show about 0.9 blocks per sq ft.
The wastage percentage is added to every line.
Worked example
A G+1 house of 1,200 sq ft per floor is 2,400 sq ft built-up. That is about 960 cement bags, 9.6 tonnes of steel, 43 brass of sand, 32 brass of aggregate and 19,200 bricks, before wastage.
FAQs
Can I order materials from this estimate? Use it to budget and to check whether a contractor’s order looks sensible. Order against your engineer’s BOQ, stage by stage.
Why is my contractor’s figure different? Spans, soil, column sizes, wall layout and finishes all change quantities. A gap of more than 25% is worth asking about. See BOQ (bill of quantities).
Does this include tiles, paint and fittings? No. It covers the structure and masonry only. Use the house construction cost calculator for an all-in budget.