BOQ (Bill of Quantities)

A BOQ (bill of quantities) is an itemised document listing every work item in a construction project, such as excavation, PCC, RCC, brickwork, plastering, tiling and painting, with its description, unit, measured quantity and rate. Contractors quote rates against the same BOQ, so their prices can be compared line by line, and the BOQ later becomes the basis for measuring and paying for work.

Also known as: BOQ, bill of quantity, schedule of quantities, estimate (loosely).

Quick facts

Prepared byQuantity surveyor, engineer or architect, from drawings and specifications
Each line hasItem description, specification, unit (m³, m², kg, nos, RFT), quantity, rate, amount
Measurement rulesIS 1200 (method of measurement)
Used forTendering, comparing quotes, cost control, RA bills
RelatedQuantity takeoff, rate analysis, item rate contract

BOQ explained

A single “rate per sq ft” hides hundreds of decisions. A BOQ makes them visible: how many cubic metres of RCC, how many kilograms of steel, how many square metres of tiles of which grade. When three contractors quote against the same BOQ, you can see exactly where one is cheaper (perhaps lower tile allowance) or more expensive (perhaps higher steel rate), instead of comparing round numbers.

During construction, the BOQ becomes the yardstick for progress payments: work done is measured, multiplied by the agreed rate and billed. Items outside the BOQ become variations, which should be priced and approved in writing before they’re done. For an individual house, even a simple BOQ prepared by your engineer is one of the best protections against cost overruns.

How buyers get cheated

  • Quantities padded. A contractor-prepared BOQ with inflated quantities. Have an independent engineer check it against drawings.
  • Vague items. “Tiling — lump sum”. Insist on units, quantities and specifications for every line.
  • Low rates, high variations. A cheap BOQ quote that recovers money through “extras”. Check what’s missing.

Related terms

Quantity takeoff · Rate analysis · Item rate contract · Measurement book · RA bill · Variation (extra item) · Quantity surveyor

Go deeper

Frequently asked questions

Do I need a BOQ for building a house?

It’s not mandatory, but it makes quotes comparable and costs controllable. Even a simple BOQ for the main items helps.

What is the difference between BOQ and estimate?

An estimate predicts total cost. A BOQ lists itemised quantities that contractors price; with rates added it becomes a detailed estimate and then a contract document.

Who prepares the BOQ?

Ideally an independent engineer, architect or quantity surveyor working for you, not the contractor who will quote against it.

Review and sources

  • IS 1200, Method of Measurement of Building and Civil Engineering Works