Enter the plastered area and thickness to get the cement bags and sand needed for the mortar.
Sand: –
How it is calculated
Wet mortar volume = area × thickness. Dry volume = wet volume × 1.27 (a standard allowance for voids in the sand and cement). Cement volume = dry volume ÷ (1 + sand parts). Sand volume = dry volume − cement volume. Cement is converted to bags at 0.0347 m³ per 50 kg bag (cement density about 1,440 kg/m³), then wastage is added and rounded up.
Worked example
100 m² at 12 mm is 1.2 m³ of wet mortar. Dry volume = 1.2 × 1.27 = 1.524 m³. At 1:4, cement = 1.524 ÷ 5 = 0.305 m³, which is 8.8 bags, so 9 bags with wastage. Sand = 1.524 − 0.305 = 1.219 m³.
FAQs
Is 1:4 the right mix? It is common for plastering. Your engineer or the plaster specification sets the mix for your job.
Why does the cement density matter? The bag count is only as accurate as the density used. Check with your supplier if the bag size differs.