Enter your contract value and floors. The planner splits it into stage payments tied to work you can check on site. The percentages are an example split; change them to match your agreement.
| Stage (pay when this is complete) | % | Amount | Paid so far |
|---|
How to use it
- Keep the advance small. A large advance is the main risk with contractors who stop work; see advance-and-abandon contractor.
- Tie every payment to a finished, checkable stage, not to a date.
- Hold back a retention amount (often around 5%) until defects found after handover are fixed.
- Write the schedule into the contract, with the scope from your BOQ.
Worked example
With a ₹30,00,000 contract and two slabs, the example split pays ₹1,50,000 as advance, ₹3,00,000 when the foundation is done and ₹5,25,000 for each slab. The final ₹1,50,000 retention is paid after the defect period.