Construction Payment Schedule Planner: Pay Your Contractor by Stage

Enter your contract value and floors. The planner splits it into stage payments tied to work you can check on site. The percentages are an example split; change them to match your agreement.

Stage (pay when this is complete)%AmountPaid so far

Pay each stage only after you or your engineer have checked the work. Keep receipts for every payment.

How to use it

  • Keep the advance small. A large advance is the main risk with contractors who stop work; see advance-and-abandon contractor.
  • Tie every payment to a finished, checkable stage, not to a date.
  • Hold back a retention amount (often around 5%) until defects found after handover are fixed.
  • Write the schedule into the contract, with the scope from your BOQ.

Worked example

With a ₹30,00,000 contract and two slabs, the example split pays ₹1,50,000 as advance, ₹3,00,000 when the foundation is done and ₹5,25,000 for each slab. The final ₹1,50,000 retention is paid after the defect period.