Sand Calculator: Sand for Concrete, Mortar and Plaster (Brass and Cu Ft)

Pick the work, enter its wet volume, and get the sand needed. For plaster, multiply the area by the thickness to get the volume first, or use the plaster calculator.

1 m³ = 35.3 cu ft
Sand needed: –

How it is calculated

Dry volume = wet volume × 1.54 for concrete or × 1.33 for mortar and plaster, to allow for voids and bulking. Sand = dry volume × sand parts ÷ total parts, plus wastage. 1 brass = 100 cu ft.

Worked example

1 m³ of M20 concrete: dry volume 1.54 m³; sand is 1.5 of 5.5 parts, so 0.42 m³, about 14.8 cu ft, or 0.15 brass before wastage.