Curing of Concrete

Curing is keeping freshly placed concrete, plaster or masonry continuously moist and protected for a set number of days after it is laid. Cement needs water to complete the chemical reaction that gives it strength. If the surface dries out early, especially in hot Indian summers, the concrete ends up weaker, more porous and prone to cracks, no matter how good the mix was.

Also known as: watering, “giving water to the slab”, ponding (one method).

Quick facts

Minimum periodAt least 7 days for OPC concrete; at least 10 days with blended cement (PPC, PSC) or mineral admixtures; longer in hot, dry weather (IS 456)
MethodsPonding water on slabs, wet hessian or gunny bags, regular spraying, plastic sheets, curing compound
StartsAs soon as the surface has set enough not to be damaged, usually within hours
Applies toSlabs, beams, columns, plaster, brickwork, blockwork, screeds
StandardIS 456 (curing clause)

Curing explained

Concrete doesn’t harden by drying; it hardens by hydration, a reaction between cement and water that continues for weeks. In the first few days the reaction is fastest and most important. Sun and wind can pull water out of the surface faster than the reaction uses it, leaving a weak, dusty top layer and fine cracks. Proper curing keeps water available so the cement can develop its full strength and a dense, durable surface.

On house sites, slabs are usually cured by building small mortar bunds and flooding them with water (ponding). Columns and beams are wrapped in wet hessian. Vertical plaster is sprayed several times a day. Blended cements such as PPC gain strength slowly and need longer curing, which matters because PPC is the most common cement in Indian homes.

How buyers get cheated

  • Curing stopped early. After two or three days the crew moves on and nobody waters. Write the curing period into the contract and check daily.
  • Only the top is cured. Columns and beam sides are left dry. Look for wet hessian on vertical elements.
  • Water bills shifted. Agree up front who pays for curing water and tankers.

Related terms

Curing compound · Ponding test · Plastic shrinkage cracks · Hot weather concreting · PPC cement · Cube test · RCC

Go deeper

Frequently asked questions

How many days should a slab be cured?

IS 456 sets minimums of about 7 days for OPC and 10 days for blended cement, with longer periods in hot, dry weather. Many engineers ask for 14 days on slabs. Follow your engineer’s instruction.

What happens if concrete is not cured?

It reaches lower strength, its surface becomes dusty and porous, and shrinkage cracks appear. Over time, water and air reach the steel more easily, which shortens the life of the structure.

Does plaster need curing?

Yes. Cement plaster should be kept moist for several days after application, or it cracks and sounds hollow. Spray it regularly, especially on sun-facing walls.