Slab casting is the complete operation of constructing a reinforced concrete floor or roof slab: preparing and levelling the shuttering, placing and checking reinforcement and conduits, pouring and vibrating concrete, finishing the surface to level or slope, and curing it. On Indian house sites it is usually done in one continuous day and is treated as a milestone for each floor.
Also known as: slab pour, roof casting, “slab day”, taarasi (Kannada for terrace).
Quick facts
| Before | Shuttering level check, steel inspection, conduit and sleeve placement |
| During | Continuous pour, vibration, slump checks, cube sampling |
| After | Surface finishing, curing, de-shuttering after specified time |
| Concrete | Site-mixed or ready-mix, as per design grade |
| Codes | IS 456, IS 4926 (RMC) |
Explained
A slab is the largest single concrete element in a house, so planning matters. The day before, the engineer checks the shuttering is level and well propped, that bar sizes and spacing match the drawing, that extra top bars and cranks are in place, and that electrical conduits, fan boxes and plumbing sleeves are fixed. Missing a sleeve means breaking concrete later.
On the day, enough labour, materials and two vibrators should be ready. Concrete is placed in a planned sequence so that no part sits too long before the next batch joins it. The surface is levelled, given any required slope for terraces, and then kept wet. Many families in Karnataka mark the occasion with a small puja.
Curing should continue for the period specified by the engineer, often by ponding water on the slab.
How buyers get cheated
- Thin slab. Measure slab thickness at the edges and at shuttering joints before and after pouring.
- Steel missing in places. Check extra top bars over beams and at cantilevers against the drawing.
- Curing stopped early. Check ponding continues for the specified days.
Related terms
Concrete pouring · Reinforcement binding · De-shuttering time · Curing · Two-way slab · Extra top bar · Terrace slope
Go deeper
Frequently asked questions
What should I check before slab casting?
Shuttering level and props, bar sizes and spacing, top bars and cranks, cover blocks, conduits and fan boxes, plumbing sleeves and drain outlets. Ideally your engineer signs a pre-pour checklist.
Should a slab be cast in one go?
Yes, where possible. If a break is unavoidable, it should be at a construction joint location the engineer has approved, not wherever the concrete ran out.
How long should a slab be cured?
IS 456 calls for curing for a minimum period depending on cement type and weather, often at least 7 days for OPC and longer for blended cements. Follow your engineer’s advice.
Review and sources
- IS 456:2000, Plain and Reinforced Concrete — Code of Practice
- IS 4926, Ready-Mixed Concrete — Code of Practice
Related: Concrete pouring · Centring and shuttering · Concrete calculator · BuildPedia